December 26, 2025Renovating a kitchen or bathroom is an exciting project, but it helps to understand what actually happens from start to finish. Having a clear renovation timeline not only keeps your project organised but also helps you manage expectations, plan your budget, and avoid unnecessary delays. Every renovation is different, but most follow a similar process. Here’s a simple breakdown of what happens first, what comes next, and how long each stage typically takes.
1. Planning and Design (1–3 Weeks)
Planning is the first step in your renovation timeline. This stage is where everything begins. This is the time to clarify your goals, measure your space, and decide what needs to be changed. Whether you’re upgrading cabinetry, redesigning the layout, or refreshing outdated fittings, planning sets the foundation.
During this stage, you’ll select colors, materials, and fixtures while working out your budget. The clearer your plan, the smoother your renovation will be.
2. Ordering Materials and Fixtures (2–6 Weeks)
Once your design is locked in, it’s time to order everything needed for the project. This includes cabinets, tiles, benchtops, tapware, vanities, and accessories. Some materials are readily available, while others may require a longer lead time.
Ordering early ensures everything is ready when your trades begin work, keeping the renovation on schedule.
3. Demolition and Removal (1–3 Days)
When the renovation starts, the old items have to come out. This includes removing cabinets, benchtops, tiles, or vanities. Demolition doesn’t take long, but it needs to be done safely and carefully to protect the structure of your home.
Once everything is cleared, the space is ready for the next phase.
4. Plumbing and Electrical Work (2–5 Days)
Before anything new goes in, plumbing and electrical adjustments happen. This might involve installing new pipes, wiring for lighting, or preparing connections for appliances and fixtures.
This step is crucial because it ensures your renovation meets safety standards and supports your new layout.
5. Flooring, Waterproofing, and Tiling (1–2 Weeks)
If you’re renovating a bathroom or changing the kitchen floor, this is when the new flooring is installed.
In bathrooms, waterproofing must be applied before tiles go in. This process requires drying time, which can take a few days.
Then the tiling begins. Depending on the size of the space and the tile design, this step can take anywhere from a week to two weeks.
6. Cabinetry and Benchtop Installation (3–7 Days)
Cabinet installation is one of the most exciting stages because the transformation becomes visible.
Kitchen cabinetry, bathroom vanities, and storage units are installed carefully to ensure perfect alignment.
Benchtops may be installed on the same day or require a separate visit, especially if custom-made.
7. Fixtures, Fittings, and Final Touches (2–5 Days)
This is when your renovation truly comes together. Tapware, mirrors, handles, lighting, and accessories are added.
Appliances are connected, sinks are installed, and final adjustments are made.
At this stage, the room looks polished and ready to use.
8. Final Inspection and Clean-Up (1 Day)
The final step in renovation timeline involves checking everything to ensure it functions correctly. Any small touch-ups are completed, and your new space gets a thorough cleaning.
Once everything is approved, your renovation is officially complete.
FAQs
How long does a full kitchen or bathroom renovation usually take?
Most renovations take between 3–8 weeks depending on the size, materials, and complexity of the project.
What stage takes the longest during a renovation?
Material ordering and tiling typically take the most time, especially if items are custom-made.
Can I stay at home during the renovation?
Yes, most people stay home—especially during kitchen renovations Mulgrave—although bathrooms may require temporary adjustments.